Subject: Sardar Sarovar Project Overview
/* Written 12:10 pm May 31, 1994 by patrickirn@igc.apc.org in igc:env.dams */
/* ---------- "Sardar Sarovar Project Overview" ---------- */
SARDAR SAROVAR PROJECT (SSP)
AN OVERVIEW
May 30, 1994
Compiled by Patrick McCully of International Rivers
Network from a variety of Indian government,
World Bank, Narmada Bachao Andolan and
independent sources.
Hard copy versions are available for $4 from the
address at the end of the report (checks payable
to International Rivers Network).
Contents:
Location
Dam Dimensions
Associated Infrastructure
Dam Bureaucracy
Construction Schedule
Construction in 1994
World Bank Involvement
Claimed Benefits
Financial Cost
How to Meet Gujarat's Water Needs
Submergence and Displacement
Resettlement Conditions
Position of the Madhya Pradesh Government
Indian Review Committee
-----------------------------------------
The first recorded proposal for damming the Narmada River
and diverting its water to irrigate crops in Gujarat was
made by a British entrepreneur in 1863. The first serious
study of the development of the whole basin began in 1947.
After independence these investigations were taken up by
various government committees which proposed numerous dams
on the Narmada and its tributaries. The first proposal for a
dam at the Sardar Sarovar site was made in 1959 and
preliminary construction began in 1961. Disagreements
between the states through which the Narmada flows about how
to share its water, however, led to the project being
suspended. In 1969 the Narmada Water Disputes Tribunal
(NWDT) was set up to decide the inter-state allocation of
water and the costs of the dams and other infrastructure
needed to exploit the river. The tribunal's decision or
'Award' was made in 1979. Full-scale construction of Sardar
Sarovar began in 1987.
Location
The Sardar Sarovar Dam is on the Narmada River in Gujarat
state, 170 kilometres (106 miles) upstream from where the
river flows into the Gulf of Khambhat in the Arabian Sea.
The Narmada is the largest westward flowing river in India.
A few kilometres downstream from the dam site on the north
bank is Kevadia Colony, the town built to house the
construction workers and related bureaucracy. Vadgam, the
first village behind the dam, starts around one kilometre
from the dam site and stretches out for several more
kilometres along the north bank. About 15 km upstream on the
south bank a small tributary running into the Narmada forms
the Gujarat-Maharashtra border. On the eastern (Maharashtra)
side of the creek is the village of Manibeli, a focus of
resistance to the project where the Narmada Bachao Andolan
(NBA -- Save the Narmada Movement) maintains an office.
Dam Dimensions
The dam is a 1210 m (3970 feet) long wall of concrete across
the valley. It is designed to impound a reservoir with a
full level of 139 m (455 feet) above sea level (asl). The
middle section of the dam is planned to reach a height of
146.5 m (481 feet) asl. The bed of the river at the dam site
is at 17 m (56 feet) asl so the planned height of the dam
above the river bed is 129.5 m (425 feet).
Associated Infrastructure
The main canal leading from the reservoir is scheduled to be
460 km (286 miles) long, eventually reaching the state of
Rajasthan. It is 250 m (820 feet) wide at its head near the
dam and planned to be 100 m (328 feet) wide at the Rajasthan
border. A network of secondary canals totalling 75,000 km
(46,600 miles) in length is planned to deliver the
irrigation water to farmers. Large electric-powered pumping
stations will need to be built to deliver water to the
Saurashtra and Kutch branches of the canal system. A large
powerhouse containing turbines and related machinery is
being built at the dam and a smaller one at the head of the
canal. A weir is to be built at Garudeshwar, around 16
kilometres downstream of the dam, with a capacity to store
six hours of the maximum flow through the Sardar Sarovar
turbines. This water can be pumped back into the reservoir
at times of low daily electricity demand and then released
through the turbines again to generate electricity at times
of peak demand.
Dam Bureaucracy
To oversee the implementation of the dams on the Narmada the
NWDT set up the Narmada Control Authority (NCA) composed of
senior representatives of the governments of Gujarat,
Maharashtra, Madhya Pradesh (MP) and Rajasthan, and chaired
by the Water Resources Secretary (the top civil servant in
the central government Ministry of Water Resources). The NCA
has established Environment and Rehabilitation Sub-Groups,
chaired respectively by the Secretaries of the central
government Ministry of Environment and Forests (MoEF) and
the Ministry of Welfare. SSP is being implemented by the
Sardar Sarovar Narmada Nigam Ltd (SSNNL or 'the Nigam'), a
corporation wholly owned by the Government of Gujarat (GoG).
The construction of the dam is contracted to Jay Prakash
(J.P.) Associates, who have a virtual monopoly over major
dam projects in India, and the construction of the canals to
a number of smaller contractors.
Construction Schedule
Completion of the dam is scheduled for 1997. The canal
network will not be finished until 2025 at the earliest. The
annual construction schedule varies between different
official sources. At the start of the monsoon in June 1993 -
the end of the 1992/93 construction season - the lowest
blocks of the dam were at 61 m asl (the sides of the dam are
much higher). The lowest blocks are currently (mid-May,
1994) at 69-70 m with the rest of the middle section of the
dam at 80 m.
Construction in 1994
According to a Supreme Court decision of August 1990,
'oustees' (the people to be displaced by the reservoir)
should be properly resettled at least six months before
submergence of their homes or lands. Concerns over the slow
pace of resettlement and unfinished environmental studies
led the NCA Environment Sub-Group to recommend in late 1993
that the dam should not be built above 67 m asl during the
1993/94 construction season and that the temporary
construction sluice gates at the foot of the dam should not
be closed. The NCA accepted this recommendation. The sluice
gates allowed the river - outside of the monsoon - to flow
under the dam and prevented any permanent impoundment of
water. During the monsoon (generally early June to late
August), the small temporary sluices could pass only a small
fraction of the swollen river and the rest of the water
would back up and flow over the top of the dam.
At the beginning of January 1994, work on raising the dam
was suspended with the height of the lowest blocks already
above the NCA's height limit, at around 69 m. On January 11,
a statement issued after a meeting in New Delhi between
Prime Minister Narasimha Rao and the Chief Ministers of
Gujarat, Maharashtra and MP, said that there would be no
further construction above 67m unless people were
rehabilitated 'well ahead of time' (the statement falsely
claimed that the dam was then at 61 m). On February 23,
however, the dam authorities without notice closed the steel
shutters on the ten temporary sluice gates and started to
raise the dam wall again.
The day after the sluices were closed the Gujarat High
Court stayed any further work on closure of the sluices,
preventing the authorities from permanently filling the
sluices with concrete. The authorities told the High Court
that the chains on the steel shutters had been cut making
the closure irreversible. Within two weeks of the closure
the river rose to the height of the next set of openings in
the dam, the 'river sluices' at 53 m asl. The level of the
water behind the dam is now around 60 m. Houses and fields
in four villages have been flooded and access roads cut off.
The number of families to be affected by submergence
during the coming monsoon will depend upon how much further
the dam is raised and how much rain falls. There are no
gates in the dam which can be opened to let flood waters
through. Official estimates of the number at risk during
each monsoon are based on calculations of the height of
water in a 1 in 100 year flood. The Government of
Maharashtra (GoM) has cited figures for the number of
families at risk in the state this year which range from 148
to over 2000. The NBA says that 500 families in Maharashtra
are at risk of losing their houses and many more will lose
crops. GoG claims that all its oustees have been resettled:
the NBA says that 400-500 families in Gujarat are still in
areas at risk this year. The Government of MP (GoMP) now
says 15 villages are at risk, three of which could be
totally submerged. In total, the NBA believes that at least
40 villages are at risk in the three states.
Shripad Dharmadhikary of the NBA wrote in early May about
what is likely to happen during this monsoon:
"Most families would be stranded . . . or dumped by
the government at inadequate, ill-prepared
'resettlement' sites . . . Many families would face
a worse situation as the rising waters would fill up
the numerous streams and gullies, cutting off access
roads, and slowly turning the undulating region into
a series of isolated islands . . . The houses could
be marooned for as long as 4-6 months."
The families threatened are not only those who have
refused to move because of their opposition to SSP, but also
many who have accepted that the dam will be built and have
asked for resettlement but who have not been given anywhere
to go.
World Bank Involvement
The World Bank agreed to lend $450 million for SSP in 1985.
After years of criticism the Bank in 1991 commissioned a
team of four independent experts to review the resettlement
and environment components of the project. The Independent
Review was chaired by an ex-head of the UN Development
Programme, Bradford Morse. His deputy was Thomas Berger, a
Canadian lawyer known for his work on human rights and
environmental issues. Their report, released in June 1992,
strongly criticised the project and the World Bank's
involvement in it, concluding that:
". . . the Sardar Sarovar Projects as they stand are
flawed, that resettlement and rehabilitation of all
those displaced by the Projects is not possible
under prevailing circumstances, and that the
environmental impacts of the Projects have not been
properly considered or adequately addressed.
Moreover, we believe that the Bank shares
responsibility with the borrower for the situation
that has developed."
The international pressure on the World Bank to withdraw
built up over the following months. Finally the Bank
realized that the damaging publicity SSP was creating was
going to get worse and that it needed to find a face-saving
method of extricating itself from the project. It decided
that the best course of action for both itself and the
Indian government was for GoI to request the Bank to pull
out. A deal was made and on March 30, 1993, India formally
requested the Bank to cancel the $170 million remaining to
be disbursed for the project. Around half the money spent on
the project so far has come from the World Bank.
On the same day as the loan was cancelled the Bank's
General Counsel, Mr Ibrahim Shihata, wrote a memorandum
reminding the South Asia Department that notwithstanding the
cancellation all the provisions of its 1985 loan agreements
were still in place. The agreements contain several
conditions on the resettlement and rehabilitation of the
people to be displaced. The World Bank is thus still legally
bound to ensure that the project authorities comply with
these provisions. These conditions are being widely and
comprehensively broken. Non-project specific loans from the
World Bank to India may still be helping to fund SSP.
Claimed Benefits
SSP's backers claim the project will irrigate a 'command
area' of 1.8 million hectares (4.45m acres) in Gujarat and
75,000 hectares (185,000 acres) in Rajasthan; have an
installed power generation capacity of 1450 megawatts;
provide domestic water to over 2.35 million people in 8235
villages and 135 towns in Gujarat; and prevent flooding
downstream.
Narmada Flow: The NWDT allocated the Narmada water on
the assumption that in three out of every four years at
least 28 million acre feet (MAF) (34.5 billion cubic
metres) of water flowed down the river. However
measurements of the actual flow between 1948 and 1993
show that the 75% dependable flow has been only 22.75
MAF. This reduces the share of water available to
Gujarat by at least 16%.
Irrigation Efficiency: The irrigation efficiency of SSP
(the amount of irrigation water which actually reaches
crops) is assumed in project documents to be 60%.
Experience with existing irrigation schemes and
independent studies of the SSP irrigation plans
indicate that this is unrealistically high. The World
Bank's 1991 'India Irrigation Sector Review' states:
"Irrigation efficiency in India has often been
assumed at 60%, whereas a worldwide sample of
irrigation commands indicates 37-40% efficiency
in areas of low rainfall under reasonably good
management, and in higher rainfall zones, an
average of 23%. Most irrigation commands in
India probably have an irrigation efficiency of
20-35%. If assumed efficiency is 60% and actual
efficiency is 30%, actual water availability
will be half the assumption at design."
Narmada Sagar: The potential benefits of SSP are based
on the assumption that it will be able to exploit
regulated releases of water from the Narmada Sagar
Projects (NSP) upstream in Madhya Pradesh. NSP (which
consists of one major dam (Narmada Sagar) and two
medium ones (Omkareshwar and Maheshwar)) and SSP are
supposed to work as part of a single system. The NWDT
stated that MP should "complete the construction of
Narmada Sagar Dam . . . concurrently with or earlier
than the construction of Sardar Sarovar Dam." According
to the World Bank's 1985 Staff Appraisal Report for
SSP, NSP would be operational by 1993. However,
construction on Narmada Sagar began only in 1992 and is
now virtually at a halt with the dam not yet above
foundation level. The Chief Minister of MP has recently
said that the state does not have the money to continue
NSP or other dams on the Narmada. According to the
NWDT, without Narmada Sagar the irrigation water
available to SSP would be reduced by at least 17%;
according to the World Bank, the available water would
be reduced by 30%. British hydrological consultants HR
Wallingford (commissioned by the World Bank in 1992),
concluded that the Sardar Sarovar reservoir would fill
up with sediment two to three times faster - severely
shortening the lifetime of the project - if NSP is not
built.
Unsuitability of Land for Irrigation: Large parts of
the area slated to be irrigated have soils which are
highly prone to waterlogging and salinization and are
unsuited to canal irrigation.
Water Intensive Crops: Despite assertions from GoG that
water-intensive sugar cane growing will not be allowed
in the SSP command area, five large sugar cane
factories are being built close to the head of the main
canal. Whilst the area to be irrigated has been
calculated on the assumption that an average of 320 mm
of water will be delivered to the fields each year,
sugar cane requires up to 3000 mm. If water is heavily
consumed by sugar cane plantations in the initial
reaches of the canal system, much less water will be
available for users further from the dam.
Little Water for Most Drought-Prone Areas: The project
proponents claim that SSP will solve the severe drought
problems of Kutch and Saurashtra, the two driest parts
of Gujarat. However only 1.6% of the total cultivable
land of Kutch and 9.24% of the cultivable land of
Saurashtra are in the SSP command area. Both these
areas are at the tail end of the canal system and will
be severely affected by the water shortages in the
system - all the available water is likely to be
consumed by the less needy areas of central Gujarat
before it ever reaches Kutch and Saurashtra. The
central government and the World Bank have stated that
the infrastructure to deliver water to Kutch will not
be fully developed until 2025 AD. Gujarat is currently
spending 80% of its total irrigation budget on SSP,
depriving smaller irrigation and water supply projects
in Kutch and Saurashtra of funds. These projects could
help alleviate the water crisis in the drought-prone
areas of Gujarat decades before they have a chance of
getting water from the Narmada.
Power Benefits: The power from SSP is to be generated
from a 1200 MW powerhouse at the dam and a 250 MW
powerhouse at the head of the canal. However the power
actually produced will be much less than the installed
capacity, mainly because increasing amounts of water
will be diverted into the canals, reducing the volume
of water available to flow through the turbines at the
dam. When the canal network is fully developed the dam
powerhouse will become redundant as only the highest
monsoon flood flows will be allowed to pass downstream.
GoG's own figures show that firm power generation will
drop from 425 MW during the first stage of the project
to a meagre 50 MW at full irrigation development.
Without NSP the power generation potential of SSP will
be reduced by a further 25-28% according to World Bank
and GoG figures. As 16% less water is available in the
Narmada than assumed by the NWDT, the power benefits
will be reduced further.
According to the NWDT, Gujarat will get only 16% of
the power from SSP, the rest being split between
Maharashtra (27%) and MP (57%). Pumping water to the
Kutch and Saurashtra branch canals would consume around
70 megawatts after allowing for the small amounts of
power generated by turbines in the canal system. Large
amounts of power would also be required to pump
groundwater into the canals, an integral part of the
irrigation plans; to drain the command area soils; and
to operate the gates and other structures regulating
the flow in the canals.
Drinking Water: No plans have been completed for how
the drinking water is to be delivered to consumers, nor
has any money been allocated for this component of the
project. In 1992 an NCA publication estimated that tens
of billions of rupees ($1 = c.30 rupees) would be
required to provide drinking water for the villages of
Kutch and Saurashtra. Gujarat's water allocation under
the NWDT Award did not allow for any village water
supply. The Nigam Chairman admitted in 1992 that 236 of
the villages supposed to receive water are in fact
uninhabited, an illustration of how the drinking water
benefits have been exaggerated.
Flood Control: SSP will severely restrict downstream
flows, encouraging people to move into the areas now
prone to flooding. The reservoir, however, has not been
designed to hold back the occasional large floods at
the end of the monsoon, when the reservoir will already
have been filled in preparation for the next dry season
and will therefore have no spare flood storage
capacity. Hydrological consultants HR Wallingford state
that: "Prior to Narmada Sagar Dam, a large flood
occurring in the second half of the monsoon period may
be attenuated by less than 20% . . . The principal
danger is that reduced flood risk will lead to
encroachment onto the flood-prone land which may negate
any [flood control] benefit obtained [from SSP]."
Financial Cost
There are no firm estimates for the total financial cost of
SSP. In 1983 the project authorities' submission to the
World Bank estimated the cost at 42,040 million rupees in
1981-82 prices, including the canals but not the
infrastructure for supplying drinking water. In 1985 the
World Bank estimated the cost as Rs.136,400 million. In
1991, GoG revised its estimate upwards to Rs.90,000 million.
In 1993 it was revealed that this figure does not include
interest of over Rs.17,000 million. The NBA's detailed
analysis estimates the total project cost at current prices
including canals and water distribution as at least
Rs.250,000 million ($8,300 million). A 1994 World Bank
publication cited the project cost as $11,400 million
(Rs.342,000 million).
GoG has unsuccessfully attempted to privatize the
hydropower component of the project in the last few years.
The privatization prospectus put the cost of the power
component at Rs. 29,000 million - eleven times greater than
the cost cited in the 1979 NWDT Award. The termination of
Japanese and World Bank aid, and the large arrears in the
mandatory financial contributions from Maharashtra and MP
are putting further pressure on Gujarat.
In 1985 the World Bank calculated the values of different
parameters at which the project's net financial benefit
would become zero. Some of these are:
* Total cost +15%
* Total benefits -13%
* Power benefits -38%
* Dam implementation period +22%
* Irrigated yield -15%
These are single parameter values, all of which will clearly
be exceeded. Taking the combined effect of the changes in
the parameters, the financial cost of the project must
vastly exceed its potential financial benefit.
How to Meet Gujarat's Water Needs
As the project is clearly not going to perform as claimed,
what are needed are not 'alternatives' to SSP, but ways of
solving Gujarat's water crisis, and especially the water
shortages in Kutch and Saurashtra. Several plans have been
developed by engineers and economists (with a minuscule
fraction of the resources put into planning SSP) which show
how Gujarat could fulfil the promised benefits of SSP
without its massive financial, human, and environmental
costs, and much more quickly. GoG's own water agencies have
stated that it is possible to deliver water to Kutch and
Saurashtra much more cheaply and quickly than could be
possible with SSP.
Ashvin Shah, a Gujarati working with the American Society
of Civil Engineers, notes that SSP is based on outmoded
1950s ideas of water development, and its planning has
failed to benefit from the past four decades of experience
with irrigation and water conservation schemes in India and
elsewhere. With the large scale implementation of
decentralized, small rainwater harvesting schemes, claims
Shah, 21 MAF of rainwater could be collected within Gujarat
each year, 50% more than the amount of water supposed to be
made available by SSP. Shah's plan to solve Gujarat's water
crisis is based on a more equitable sharing of the available
water, water harvesting, water conservation, making existing
water supply and irrigation schemes more efficient, the
restoration of degraded watershed vegetation, and making
farming practices less water and energy intensive. He also
advocates the exploitation of Gujarat's wind, solar, tidal
and biomass energy resources.
Submergence and Displacement
The NBA believe that over one million people will lose land
or be otherwise severely affected by the various components
of the project. As comprehensive surveys have not been
completed by the dam authorities the following figures are
all estimates.
Reservoir: Around 91,000 acres (37,000 ha) in Gujarat,
Maharashtra and Madhya Pradesh (MP) will be flooded by
the 133 mile (213 km) long reservoir. About 28,660
acres (11,600 ha) of this land is officially classified
as 'forest land' although the actual amount of tree
cover on forest land varies greatly. Official estimates
of the number of families to be displaced (called
Project Affected Persons or PAPs - a 'PAP' is a family
unit rather than a person) have increased around six-
fold since 1979. The latest official estimates from the
three states add up to 41,500 PAPs, or 207,500 people,
around 80% of them in Madhya Pradesh. Almost all the
PAPs in Gujarat and Maharashtra and perhaps half of
those in MP are adivasis, or tribal people, belonging
to a number of different groups collectively referred
to as Bhils. The adivasis to be displaced by the
reservoir live mainly in 14 villages in Gujarat, 33 in
Maharashtra and around 53 in MP. The adivasi areas are
mostly remote and hilly with few social services. The
adivasis are largely self-sufficient, growing their own
food and collecting fuel, building materials, fodder,
fruits, and other resources from the forests and
commonlands around their villages, as well as relying
on water and fish from the river. The non-tribal PAPs
in MP live in around 140 villages in the furthest
upstream part of the submergence zone, the rich
agricultural plain known as the Nimad. There are also
some adivasis living in this area.
Canals: Over 200,000 acres (80,000 ha) of land in
Gujarat will be lost to the canal network if it is ever
completed. Estimates for the number of landholders to
be affected by the canals range from 140,000 to
222,800. The World Bank estimated in 1992 that 24,000
of these landholders would lose over a quarter of their
land (the nature of land records in Gujarat means that
each 'landholder' in fact represents 3-4 families). An
estimated 10% of the Canal Affected Families (CAFs) are
adivasis. The CAFs are not recognized as 'Project
Affected' and are not eligible for the same
compensation package as the reservoir PAPs. Families
who have already lost land to canals have received cash
compensation far below current land prices.
Sanctuary and National Parks: Over 42,000 adivasis
would be displaced by the Shoolpaneshwar Wildlife
Sanctuary in Gujarat planned to compensate for the
forests and wildlife lost to the reservoir. There are
no arrangements to resettle or compensate these people.
Two National Parks which the central Ministry for
Environment has planned for Madhya Pradesh would
displace thousands more people.
Downstream Displacement: The dam is planned eventually
to store and divert all of the water in the Narmada,
except during the wettest monsoons. This will dry up
the river downstream destroying the livelihood of at
least 10,000 fishworker families. It will also severely
affect the water supply to over 700,000 people in 210
villages and at least five towns.
Afforestation: Afforestation schemes supposed to
compensate for the trees lost to the reservoir are
taking over large amounts of adivasi land. Although the
adivasis have been cultivating this land for
generations they often have no legal rights to it and
therefore receive no compensation for land lost to tree
plantations.
Secondary Displacement: Large numbers of people are
dependent on the forest and agricultural land being
taken over for resettlement sites, either for resources
such as fuelwood and fodder or for employment. The
Ministry of Environment and Forests recognizes that
between 10-15,000 tribals depend on the 3,707 acres
(1,500 ha) of forest land released for resettlement of
Maharashtra PAPs by MoEF in February 1994. No measures
have been taken to compensate these people. An adivasi
woman in a group protesting against the taking over of
forest land for resettlement in Maharashtra was shot
dead by police in July 1992.
Backwater Effect: The larger sediments in the water
entering a reservoir are deposited at its upper end
forming a delta and steadily raising the level of the
upper reaches of the reservoir. A large area of
farmland, many villages and even whole towns in the
Nimad could be affected by flooding due to this
backwater effect, yet no proper study of this has been
done.
Kevadia Colony: Work on the infrastructure at Kevadia
began in 1961 and involved the acquisition of land from
six adivasi villages. Around 950 families were
displaced. These people have received little or no
compensation.
Rock-Filled Dykes: A number of holding ponds between
the reservoir and the main canal have been impounded by
rock-filled dykes, displacing around 900 families from
five adivasi villages in Gujarat between 1983 and 1991.
Marooned Land: The rugged nature of the adivasi areas
means that many families will find their houses and
lands isolated on small islands or inaccessible
peninsulas. As no proper land surveys have been done in
Madhya Pradesh, the authorities do not know how many
people will be affected in this way.
Resettlement Conditions
The resettlement package differs between the three states.
PAPs from Gujarat, or those from Maharashtra and MP willing
to move to Gujarat, are eligible for a minimum of two
hectares (five acres) of irrigable land in the command area
of the project as well as house sites and some cash
compensation. Major sons (those over 18) and landless
families (many of the tribal families cultivate land to
which they have no legal title) are also eligible for two
hectares of land under Gujarat's policy. 'Landless' oustees
and major sons settling in Maharashtra receive only one
hectare; those in MP are not eligible for any land.
The authorities claim that around 7000 PAPs have been
resettled in Gujarat and Maharashtra. No oustees have been
resettled in MP. Those who have been resettled face a
multitude of hardships and many have returned to their
original villages. The stress and impoverishment caused by
resettlement has increased death rates among the oustees,
especially of children. The problems, which have been
extensively noted by the official resettlement monitoring
agencies and the World Bank's Independent Review include:
* lack of grazing lands, firewood, drinking water, and
cremation facilities;
* poor quality, flood-prone cropland, land which is
not irrigable and plots which are less than the two
hectares promised (the supposed two hectare minimum
has in practice turned into a two hectare maximum);
* disputes over ownership of resettlement plots and
conflicts with host communities;
* villages, hamlets and even families split up among
many different resettlement sites.
GoG has acquired under 14,000 hectares of land for the PAPs
who have been resettled in the state, spread over
approximately 400 different resettlement sites. There are no
plans available describing where land will be found for the
remaining 13,000 oustees expected to move to the state. The
acquisition of such large areas of land combined with land
speculation due to SSP has greatly increased land prices in
the command area, inflating the cost to the government of
acquiring land, and encouraging the government to buy land
of increasingly inferior quality. GoM has only after great
difficulty and controversy persuaded the MoEF to release
4,300 hectares of forest land for resettlement in
Maharashtra. This is only just over half the land needed for
oustees in the state. GoMP admits that it is unable to
acquire any agricultural land for resettlement.
Position of the Madhya Pradesh Government
An important recent development has been that the new
government in Madhya Pradesh, elected in November 1993, has
admitted that MP cannot resettle the huge numbers of people
in the state to be displaced by SSP as currently planned. A
GoMP note circulated at an all-party meeting called by the
MP Chief Minister Digvijay Singh in February 1994,
recommended that the full reservoir level should be reduced
from 455 feet (139 m) to 436 feet (133 m) asl which would
spare from submergence over 8,100 hectares (20,000 acres) of
land and 38,000 people in MP alone. The NWDT decided on the
455 feet level rather than 436 feet solely on the basis of
the extra power it would provide. No water supply benefits
would be lost by reducing the height. GoMP engineers have
now calculated that as the Narmada flow is 17% less than the
NWDT assumed, the reservoir level could be reduced to 422
feet and still supply the same amount of water to the
Gujarat canals as a reservoir at 455 feet. Digvijay Singh
(an engineer by training) wrote to Prime Minister Narasimha
Rao in March 1994, saying that there was consensus among
MP's political parties that the dam height should be
reduced. GoMP has also said that it is willing to forego its
57% share of the electricity produced by SSP.
Indian Review Committee
In August 1993 the central government set up a committee to
'look into all aspects of SSP'. The committee heard
submissions from GoI, GoMP, GoM, the NBA, affected people
and independent experts. GoG boycotted the review although
Gujaratis close to the state government, including Mr C.C.
Patel, an ex-Chairman of the Narmada Nigam who has been one
of the key promoters of the project, did give evidence. The
committee was originally due to submit its report to GoI by
December 1993 but the date has been continually moved
forward and it has still not been submitted. GoG has
launched a legal action against the review in the Gujarat
High Court, on the grounds that it is illegal under the
terms of the NWDT Award. The committee's report cannot be
submitted until the case goes to the High Court, which,
under political pressure, has still not set a date for the
hearing.
-o-o-o-
Metric and imperial units have been used according to
their usage in official sources. Elevations are
presented as Above Sea Level when this is how
the statistics are normally presented by the dam
authorities.